CIP MODULE
Basis of Design:
Tank Capacity:
3000 L/5000L
Product: CIP
Solution (2% NaoH, 1.5% HNO3)
Capacity : 20000
LPH
Temp Program :
65-85 deg C
Pressure at
Outlet : 3 bar
No of circuits :
2
Process
Operation: This CIP unit is suitable for cleaning in place of process
equipments like sanitary pipes, tanks, heat exchangers, filling machines etc.
It consists water recirculation tank, CIP pressure pump, tubular heat
exchanger, and temperature control system and control panel. All the components
are built on the SS frame. Flow will be indicated and manually regulated as per
the object requirements. Initially detergents will be added into the detergent
tanks by dosing pump to get the required concentration during the product
preparation cycle. The object to be cleaned is required to be connected to the
CIP unit. In the Module the detergent solution is circulated over its detergent
tank (optional) after cleaning solution is recovered back to the tank for
reuse. Hot Water is circulated over the circulation tank and is for single use.
All heating is done in line in the heat exchanger. The control system is
automatically controls the cleaning programme, time, temperature and the
conductivity meter (optional) is used for concentration check of detergent
solution and sorting of liquids. Utilities Required (Approx): Steam at 3 bar:
800 kg/hr peak consumption per circuit Approx.
Total power: 15KW,
415V, 3 PH, 50 Hz Process
Water: 27000 LPH
during rinsing per circuit. Instrument Air, 6bar: 625 NL/Hr.
SPECIFICATIONS & SCOPE OF SUPPLY
1. CIP Pressure
pump with VFD Centrifugal pump, Alfa Laval Make, all wetted parts in SS316L,
SMS connections with single shaft seal with motor of Crompton make. VFD Danfoss
make. 2 No
2. Tubular heat
exchanger .............. Tubular Heat Exchanger with SS316 inner tubes and
SS304 outer shell. 1 set
3. Steam Control
Valve pneumatically controlled Steam control valve, Sampson make with I/P
converter and Air filter/pressure regulator. 2 No
4. Automatic
Sanitary valve pneumatically actuated Single Seat USSV valve. 1 Lot
5. AC Control
panel, Control panel cabinet, MOC: SS 304, Duly pre-wired and tested, &
consists of the following Instruments and Controls: Allen Bradley Micrologix
PLC control system Human Machine Interface (HMI), Temperature transmitters.
Alarm/Hooter with `reset’ switch Mains switch for incoming supply. Emergency stop
1 No ON/OFF lockable switch with indicating lamp for control supply. Air filter
with regulator an isolation valve to regulate the compressed air supply. 20%
spares IOS 3 No DOL Starter and provision for 6 No CIP return Pump 1 No
6.
Interconnecting pipes and fittings within Module All pipes are imported and
fittings are to make the internal welding surfaces smooth and hygienic. 1 Lot
7. Pipes and
Fittings between Module and Tank – All pipes and fittings between tank and
module to be supplied fabricated. 1 Lot
8 Magnetic Flow
Meter 2 No
9 Conductivity Meter E+H make. Used for
concentration check of detergent solution and sorting of liquids. 2 No
11 Tank
Connections on Feed Module This option defines the number of connections for
the recovery tank (optional) on the feed module. 6 No
12 Recovery
Function This includes valves and level switch on the recovery tank. Used
detergent is routed back and stored in the tank (Optional). 6 No
13 Automatic
Preparation Function This includes an internal bypass. With this option it can
be ensured that correct concentration of CIP solution is available in the
recovery tanks before start of CIP. Please note option 3 needs to be selected
for this function. 2 No
14 Dosing Pump
Includes dosing pump for detergent concentrate. The dosing pump is pneumatic,
double diaphragm, plastic type, suction pipe with foot valve is included. 2 No
15 Concentrate
Storage Tank Capacity: 500 L; MOC: SS316 for storing 50% Alkali and / or 50%
Nitric acid. 2 No
16 CIP of CIP
tanks, Pump , CT etc as per ........................ P&ID.
17 Duplex Filter
pipe in pipe type with accessories coarse strainer 1mm. 2 set
18 Flow switch
IFM make 2 No.
19 Steam utIlity
pneumatic Shut off Valve , strainer , bypass arrangement for regulating valve,
in each circuit. Pressure transmitter, Flow transmitter, Pressure gauge in
steam header in loose supply. Installation of header, Pressure switch and
Safety valve.1 Lot
19a Process
water pressure gauge, Flow transmitter and Pressure Transmitter and header is in
1 lot
20 Acid Tank
Cap-5kl MOC SS 316 insulated = 1 No
21 Lye Tank
Cap-5kl MOC SS 316 insulated = 1 No
22 Hot Water
Tank Cap-500l MOC 304 Insulated = 2 No
23 Recuperation
Tank Cap-5kl MOC 304 Uninsulated = 1 No
24 Fresh Water
Tank Cap-2kl MOC 304 Uninsulated = 1 No.
25 Proximity
Switches in loose supply and automation interlocking in TPI scope. Cabling and
installation.
26 Scada for
report Generation = 1 No
27 CIP return
Pump = 4 No.
28 I & C = 1
Job
Note : All the above components will be installed
on SS 304 SKID FRAME in compact aesthetic modular construction except recovery
tank